Le texte d’un acte luxembourgeois tel qu’il se présentait à une date, ou celui d’un acte de l’UE dans le libellé qui sert de réponse pour cette date (son libellé original ou un libellé consolidé ultérieur), article par article, tel que l’éditeur l’a écrit, avec ce qu’il faut pour le citer. L’identifiant et la date sont envoyés à ce serveur dans la requête et nulle part ailleurs, et cette page ne conserve rien.

Aujourd’hui au Luxembourg : 2026-10-31.

Lex montre le texte de la loi. Il ne dit pas ce qui s’applique à votre situation, et ce n’est pas un conseil juridique.

044 Article 44

Cité d’après 32014L0023, eng, le libellé consolidé du 2026-01-01 (la date de consolidation de l’éditeur).

Article 44 Termination of concessions Member States shall ensure that contracting authorities and contracting entities have the possibility, under the conditions determined by the applicable national law, to terminate a concession during its term, where one or more of the following conditions is fulfilled: (a) a modification of the concession has taken place, which would have required a new concession award procedure pursuant to Article 43; (b) the concessionaire has been, at the time of concession award, in one of the situations referred to in Article 38(4) and should therefore have been excluded from the concession award procedure; (c) the Court of Justice of the European Union finds, in a procedure pursuant to Article 258 TFEU, that a Member State has failed to fulfil its obligations under the Treaties by the fact that a contracting authority or contracting entity belonging to that Member State has awarded the concession in question without complying with its obligations under the Treaties and this Directive.

Empreinte du texte 2110aa3d56ee1a5b5c783c14cbcdcf56bb4b8a8577e12b70a94cc84e4505ab0b, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/044

Citer cet article

Citation usuelle
Article 44 of Directive 2014/23/EU
Avec son permalien
Article 44 of Directive 2014/23/EU (https://law.soufien.lu/eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/044)
Avec ses éléments de vérification
Article 44 of Directive 2014/23/EU
Permalink: https://law.soufien.lu/eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/044

CELEX: 02014L0023-20260101

Wording: the consolidated wording of 2026-01-01

Published in: the Official Journal reference is not held by this index.

Text digest (SHA-256): 2110aa3d56ee1a5b5c783c14cbcdcf56bb4b8a8577e12b70a94cc84e4505ab0b

Consulted on Lex on 2026-10-31 (date in Luxembourg).

Only the Official Journal of the European Union published in electronic form is authentic and produces legal effects (Regulation (EU) No 216/2013, Article 1(2)); this text is a reproduction read from the Publications Office's Formex package, not the authentic edition.

L’acte entier dans ce libellé

© European Union, https://eur-lex.europa.eu

Only the Official Journal of the European Union published in electronic form is authentic and produces legal effects (Regulation (EU) No 216/2013, Article 1(2)); this text is a reproduction read from the Publications Office's Formex package, not the authentic edition.

Comment lire ceci

Les dates de l’éditeur que ce site détient pour cet acte

  • Entrée en vigueur : 2014-04-17 (mention de l’éditeur, mot pour mot : DATPUB +20 V ART 54)
  • Date limite : 2019-04-18 (mention de l’éditeur, mot pour mot : B-19.12)

Dates non détenues pour cet acte : mise en application ; fin de validité. Les déclarations datées de l’éditeur que ce site détient pour cet acte n’indiquent aucune date de ce type, ce qui ne dit rien de l’existence d’une telle date.

Aucune des dates ci-dessus ne sert à choisir un libellé : chaque libellé ci-dessous porte sa propre date.

32014L0023, eng, le libellé consolidé du 2026-01-01 (la date de consolidation de l’éditeur)

Il s’agit du dernier libellé détenu : il sert de réponse pour toute date ultérieure, et une modification que l’éditeur n’a pas encore consolidée n’y figure pas.

1 autre œuvre de l’éditeur porte cette date ; avec ce même texte détenu ici : 1 ; sans texte détenu ici : 0.

/eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng

55 articles cités ; détenus sans texte : 0.

Sommaire
  1. Page 1 : Article 1 à Article 43
  2. Page 2 : Article 44 à Article 55

Page 2 sur 2 : Article 44 à Article 55.

  1. 044 Article 44

    Article 44 Termination of concessions Member States shall ensure that contracting authorities and contracting entities have the possibility, under the conditions determined by the applicable national law, to terminate a concession during its term, where one or more of the following conditions is fulfilled: (a) a modification of the concession has taken place, which would have required a new concession award procedure pursuant to Article 43; (b) the concessionaire has been, at the time of concession award, in one of the situations referred to in Article 38(4) and should therefore have been excluded from the concession award procedure; (c) the Court of Justice of the European Union finds, in a procedure pursuant to Article 258 TFEU, that a Member State has failed to fulfil its obligations under the Treaties by the fact that a contracting authority or contracting entity belonging to that Member State has awarded the concession in question without complying with its obligations under the Treaties and this Directive.

    Empreinte du texte 2110aa3d56ee1a5b5c783c14cbcdcf56bb4b8a8577e12b70a94cc84e4505ab0b, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/044

  2. 045 Article 45

    Article 45 Monitoring and reporting 1. In order to ensure correct and efficient implementation, Member States shall ensure that at least the tasks set out in this Article are performed by one or more authorities or structures. They shall indicate to the Commission all authorities, or structures competent for these tasks. 2. Member States shall ensure that the application of rules for the award of concession contracts is monitored. Where monitoring authorities or structures identify specific violations, such as fraud, corruption, conflict of interest and other serious irregularities, or systemic problems, they shall be empowered to indicate those violations or problems to national auditing authorities, courts or tribunals or other appropriate authorities or structures, such as the ombudsman, national parliaments or committees thereof. 3. The results of the monitoring activities pursuant to paragraph 2 shall be made available to the public through appropriate means of information. The Commission may, at the most every three years, request that Member States transmit to the Commission a monitoring report covering an overview of the most frequent causes of incorrect application of the rules for the award of concession contracts, including possible structural or recurring problems in the application of the rules, including possible cases of fraud and other illegal behaviour. 4. Member States shall ensure that information and guidance on the interpretation and application of Union law for the award of concession contracts is available free of charge to assist contracting authorities and entities and economic operators in correctly applying the Union rules.

    Empreinte du texte 5e31e25f9b24c90e0db8476baf314fdd8c7f4c0af6fc1408c139ebdc6809cb95, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/045

  3. 046 Article 46

    Article 46 Amendments to Directive 89/665/EEC Directive 89/665/EEC is amended as follows: (1) in Article 1, paragraph 1 is replaced by the following: ‘1. This Directive applies to contracts referred to in Directive 2014/24/EU of the European Parliament and of the Council unless such contracts are excluded in accordance with Articles 7, 8, 9, 10, 11, 12, 15, 16, 17 and 37 of that Directive. This Directive also applies to concessions awarded by contracting authorities, referred to in Directive 2014/23/EU of the European Parliament and of the Council unless such concessions are excluded in accordance with Articles 10, 11, 12, 17 and 25 of that Directive. Contracts within the meaning of this Directive include public contracts, framework agreements, works and services concessions and dynamic purchasing systems. Member States shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f of this Directive, on the grounds that such decisions have infringed Union law in the field of public procurement or national rules transposing that law. (2) in Article 2a, paragraph 2 is amended as follows: (a) the first subparagraph is replaced by the following: ‘A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.’; (b) in the fourth subparagraph, the first indent is replaced by the following: ‘— a summary of the relevant reasons as set out in Article 55(2) of Directive 2014/24/EU, subject to Article 55(3) of that Directive, or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive, and’; (3) Article 2b is amended as follows: (a) in the first paragraph: (i) point (a) is replaced by the following: ‘(a) if Directive 2014/24/EU or, where relevant, Directive 2014/23/EU does not require prior publication of a contract notice in the Official Journal of the European Union;’; (ii) point (c) is replaced by the following: ‘(c) in the case of a contract based on a framework agreement as provided for in Article 33 of Directive 2014/24/EU and in the case of a specific contract based on a dynamic purchasing system as provided for in Article 34 of that Directive.’; (b) in the second paragraph, the first and the second indent are replaced by the following: ‘— there is an infringement of point (c) of Article 33(4) or of Article 34(6) of Directive 2014/24/EU, and — the contract value is estimated to be equal to or to exceed the thresholds set out in Article 4 of Directive 2014/24/EU.’; (4) in Article 2c, the words ‘Directive 2004/18/EC’ are replaced by the words ‘Directive 2014/24/EU or Directive 2014/23/EU’; (5) Article 2d is amended as follows: (a) in paragraph 1: (i) point (a) is replaced by the following: ‘(a) if the contracting authority has awarded a contract without prior publication of a contract notice in the Official Journal of the European Union without this being permissible in accordance with Directive 2014/24/EU or Directive 2014/23/EU’; (ii) in point (b) the words ‘Directive 2004/18/EC’ are replaced by the words ‘Directive 2014/24/EU or Directive 2014/23/EU’; (b) in paragraph 4, the first indent is replaced by the following: ‘— the contracting authority considers that the award of a contract without prior publication of a contract notice in the Official Journal of the European Union is permissible in accordance with Directive 2014/24/EU or Directive 2014/23/EU’; (c) in paragraph 5, the first indent is replaced by the following: ‘— the contracting authority considers that the award of a contract is in accordance with point (c) of Article 33(4) or with Article 34(6) of Directive 2014/24/EU,’; (6) in Article 2f(1), point (a) is replaced by the following: ‘(a) before the expiry of at least 30 calendar days with effect from the day following the date on which: the contracting authority published a contract award notice in accordance with Articles 50 and 51 of Directive 2014/24/EU or with Articles 31 and 32 of Directive 2014/23/EU, provided that this notice includes justification of the decision of the contracting authority to award the contract without prior publication of a contract notice in the Official Journal of the European Union, or the contracting authority informed the tenderers and candidates concerned of the conclusion of the contract, provided that this information contains a summary of the relevant reasons as set out in Article 55(2) of Directive 2014/24/EU, subject to Article 55(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive. This option also applies to the cases referred to in point (c) of the first paragraph of Article 2b of this Directive’; (7) in Article 3, paragraph 1 is replaced by the following: ‘1. The Commission may invoke the procedure provided for in paragraphs 2 to 5 when, prior to a contract being concluded, it considers that a serious infringement of Union law in the field of public procurement has been committed during a contract award procedure falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU.’.

    Empreinte du texte 7e9752bbd0a14b06f2e50aecbd56d65c275affc89f5c3f281497d898767357bd, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/046

  4. 047 Article 47

    Article 47 Amendments to Directive 92/13/EEC Directive 92/13/EEC is amended as follows: (1) in Article 1, paragraph 1 is replaced by the following: ‘1. This Directive applies to contracts referred to in Directive 2014/25/EU of the European Parliament and of the Council unless such contracts are excluded in accordance with Articles 18 to 24, 27 to 30, 34 or 55 of that Directive. Contracts within the meaning of this Directive include supply, works and service contracts, works and services concessions, framework agreements and dynamic purchasing systems. This Directive also applies to concessions awarded by contracting entities, referred to in Directive 2014/23/EU of the European Parliament and of the Council unless such contracts are excluded in accordance with Articles 10, 12, 13, 14, 16, 17 and 25 of that Directive. Member States shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU, decisions taken by contracting entities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f of this Directive, on the grounds that such decisions have infringed Union law in the field of procurement or national rules transposing that law. (2) in Article 2a, paragraph 2 is amended as follows: (a) the first subparagraph is replaced by the following: ‘A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.’; (b) in the fourth subparagraph, the first indent is replaced by the following: ‘— a summary of the relevant reasons as set out in Article 75(2) of Directive 2014/25/EU, subject to the provisions of Article 75(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to the provisions of Article 40(2) of that Directive, and’; (3) Article 2b is amended as follows: (a) in the first paragraph: (i) point (a) is replaced by the following: ‘(a) if Directive 2014/25/EU or, where relevant, Directive 2014/23/EU does not require prior publication of a notice in the Official Journal of the European Union;’; (ii) point (c) is replaced by the following: ‘(c) in the case of specific contracts based on a dynamic purchasing system as provided for in Article 52 of Directive 2014/25/EU.’; (b) in the second paragraph, the first and the second indent are replaced by the following: ‘— there is an infringement of Article 52(6) of Directive 2014/25/EU, and — the contract value is estimated to be equal to or to exceed the thresholds set out in Article 15 of Directive 2014/25/EU.’; (4) in Article 2c, the words ‘Directive 2004/17/EC’ are replaced by the words ‘Directive 2014/25/EU or Directive 2014/23/EU’; (5) Article 2d is amended as follows: (a) in paragraph 1, (i) point (a) is replaced by the following: ‘(a) if the contracting entity has awarded a contract without prior publication of a notice in the Official Journal of the European Union without this being permissible in accordance with Directive 2014/25/EU or Directive 2014/23/EU’; (ii) in point (b), the words ‘Directive 2004/17/EC’ are replaced by the words ‘Directive 2014/25/EU or Directive 2014/23/EU’; (b) in paragraph 4, the first indent is replaced by the following: ‘— the contracting entity considers that the award of a contract without prior publication of a notice in the Official Journal of the European Union is permissible in accordance with Directive 2014/25/EU or Directive 2014/23/EU,’; (c) in paragraph 5, the first indent is replaced by the following: ‘— the contracting entity considers that the award of a contract is in accordance with Article 52(6) of Directive 2014/25/EU,’; (6) in Article 2f(1), point (a) is replaced by the following: ‘(a) before the expiry of at least 30 calendar days with effect from the day following the date on which: the contracting entity published a contract award notice in accordance with Articles 70 and 71 of Directive 2014/25/EU or with Articles 31 and 32 of Directive 2014/23/EU, provided that this notice includes the justification of the decision of the contracting entity to award the contract without prior publication of a notice in the Official Journal of the European Union, or the contracting entity informed the tenderers and candidates concerned of the conclusion of the contract, provided that this information contains a summary of the relevant reasons as set out in Article 75(2) of 2014/25/EU subject to Article 75(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive. This option also applies to the cases referred to in point (c) of the first paragraph of Article 2b of this Directive;’; (7) in Article 8, paragraph 1 is replaced by the following: ‘1. The Commission may invoke the procedure provided for in paragraphs 2 to 5 when, prior to a contract being concluded, it considers that a serious infringement of Union law in the field of procurement has been committed during a contract award procedure falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU, or in relation to Article 26(1) of Directive 2014/25/EU in the case of contracting entities to which that provision applies’.

    Empreinte du texte 8cfe9760629d2bc48f5ca576b797ea56f96c2de20c5100d5fe44ff17c00be987, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/047

  5. 048 Article 48

    Article 48 Exercise of the delegation 1. The power to adopt delegated acts is conferred on the Commission subject to the conditions laid down in this Article. 2. The power to adopt delegated acts referred to in Article 7(3), Article 9(4), Article 27(2) and Article 30(4) shall be conferred on the Commission for an indeterminate period of time from 17 April 2014. 3. The delegation of power referred to in Article 7(3), Article 9(4), Article 27(2) and Article 30(4) may be revoked at any time by the European Parliament or by the Council. A decision of to revoke shall put an end to the delegation of the power specified in that decision. It shall take effect the day following the publication of the decision in the Official Journal of the European Union or at a later date specified therein. It shall not affect the validity of any delegated acts already in force. 4. As soon as it adopts a delegated act, the Commission shall notify it simultaneously to the European Parliament and to the Council. 5. A delegated act adopted pursuant to Article 7(3), Article 9(4), Article 27(2) and Article 30(4) shall enter into force only where no objection has been expressed either by the European Parliament or by the Council within a period of two months of notification of the act to the European Parliament and the Council or if, before the expiry of that period, the European Parliament and the Council have both informed the Commission that they will not object. That period shall be extended by two months at the initiative of the European Parliament or of the Council.

    Empreinte du texte 12d26fb88198e8df9d13e73c34cdc297d48cce3a6195dc9866fa84b1ba3f43c2, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/048

  6. 049 Article 49

    Article 49 Urgency procedure 1. Delegated acts adopted under this Article shall enter into force without delay and shall apply as long as no objection is expressed in accordance with paragraph 2. The notification of a delegated act to the European Parliament and to the Council shall state the reasons for the use of the urgency procedure. 2. Either the European Parliament or the Council may object to a delegated act in accordance with the procedure referred to in Article 48(5). In such a case, the Commission shall repeal the act without delay following the notification of the decision to object by the European Parliament or by the Council.

    Empreinte du texte 13ba50507c9c864ac812074a7d778df75851bc3bbecb95b23452569c88cb69f4, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/049

  7. 050 Article 50

    Article 50 Committee Procedure 1. The Commission shall be assisted by the Advisory Committee for Public Procurement established by Council Decision 71/306/EEC. That committee shall be a committee within the meaning of Regulation (EU) No 182/2011. 2. Where reference is made to this Article, Article 4 of Regulation (EU) No 182/2011 shall apply.

    Empreinte du texte 23e3b73d8c7e155c176c728f9df5112a4193d96c91bee4e63c88f69f0621a209, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/050

  8. 051 Article 51

    Article 51 Transposition 1. Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive by 18 April 2016. They shall forthwith communicate to the Commission the text thereof. When Member States adopt those measures, they shall contain a reference to this Directive or be accompanied by such a reference on the occasion of their official publication. Member States shall determine how such reference is to be made. 2. Member States shall communicate to the Commission the text of the main measures of national law which they adopt in the field covered by this Directive.

    Empreinte du texte 80bacc81d4783400a967011bd9ca8d95ae88c7e8560375ddf005d6f2c3f07ec7, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/051

  9. 052 Article 52

    Article 52 Transitional provisions References to points (a) and (b) of Article 1(3) of Directive 2004/17/EC and to Article 1(3) and (4) and Title III of Directive 2004/18/EC Directive shall be construed as references to this Directive.

    Empreinte du texte 7cba6956e4e6265296a548193beefda36ad1bbaa7078d1cca743d18fca791119, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/052

  10. 053 Article 53

    Article 53 Monitoring and reporting The Commission shall assess the economic effects on the internal market, in particular in terms of factors such as cross-border award of contracts and transaction costs, resulting from the application of the thresholds set out in Article 8, and report thereon to the European Parliament and the Council by 18 April 2019. The appropriateness of the level of thresholds shall be examined in the context of negotiations under the GPA taking into account the impact of inflation and transaction costs. The Commission shall, where possible and appropriate, consider suggesting an increase of the threshold amounts applicable under the GPA during the next round of negotiations. In the event of any change to the threshold amounts applicable under the GPA, the report shall, where appropriate, be followed by a legislative proposal amending the thresholds set out in this Directive. The Commission shall also assess the economic effects on the internal market of the exclusions set out in Article 12 taking into account the specific structures of the water sector, and report thereon to the European Parliament and the Council by 18 April 2019. The Commission shall review the functioning of this Directive and shall report to the European Parliament and to the Council by 18 April 2021, and every five years thereafter, based on information that Member States shall provide in accordance with Article 45(3). The Commission shall make the results of the review carried out in accordance with the fourth paragraph publicly available.

    Empreinte du texte 2f7e507cc8396d76a5f86b31e0a3368e866bb0cbbc989d905bf21a692651db43, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/053

  11. 054 Article 54

    Article 54 Entry into force This Directive shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union. This Directive shall not apply to the award of concessions tendered or awarded before 17 April 2014.

    Empreinte du texte 12abb3085e25167de302d25b4f0e544fa808800b79a832fff171fad180e00d9d, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/054

  12. 055 Article 55

    Article 55 Addressees This Directive is addressed to the Member States.

    Empreinte du texte 958f2963d9c0c610a19a5ab0f7ee9fedb5409cacf225f95f443de1e17ecdc0b4, empreinte du corps e483d758b27361bb311b787d1fa53835de5985f123131c0e95fafc3b72ac5ccf, source officielle https://publications.europa.eu/resource/cellar/8d01d3a7-06cf-11f1-825d-01aa75ed71a1.0005.01, /eu-eurlex/32014L0023/2026-01-01--66ad1c3d096bcc0166eb32e7d531e13225ce720945b1702a4bfe7a261bf28554/eng/055

Ce que cette lecture ne contient pas

  • publisher_signature : no signature or attestation of the publisher is held; the digests are this index's own reading of the retained package
  • unconsolidated_amendments : an amendment the publisher has not yet consolidated is not held: the latest consolidated wording answers every later date, as dated
  • force_dates : the act's own dates are said under force_dates, as the publisher's dated statements on the act give them; none of them is used to choose a wording, each wording carries its own date, and a date the publisher records without a dated statement is not held
  • observation_time : when the publisher served the retained package is not held, so no observation time is stated
  • markup_and_notes : the Formex markup, notes and tables are not served as structure; the text is the article's searchable text, in publisher order
  • annexes : no annex text is held: annexes are not indexed as articles, so no annex is searched, quoted or exported; annexes_not_served lists the annexes the corpus classified against the publisher PDF on the members an expression was read from, with the official source to read them, and an empty list says only that the corpus classified none there, not that the act has none